Appendix 2 – Spend so far

£4.798m has been spent on the project to the end of 2024/25, there is £6.064m remaining of the budget summarised below:

Source

Total allocation

Spend to date

 Remaining

Conditions

 

 

£m

£m

£m

 

 

Levelling Up Fund (LUF) funding

7.958

3.085 

4.873

Capital, ringfenced, spend by 31st March 2026 tbc

 

LUF Capacity and capability funding

0.271

-

0.271

Revenue, unringfenced

 

National Productivity Investment Funding (NPIF)

2.133

1.213

0.920

Capital, unringfenced

 

East Sussex County Council (ESCC) Capital Funding (borrowing)

0.500

0.500

-

N/A

 

Total

10.861

4.798

6.064

 

 

 

The table below breaks down total spend to date by year:

 

 

 

Pre 2021/22 (pre LUF)

2021/22

2022/23

2023/24

 

2024/25

Total to 2024/25

 

£m

£m

£m

£m

 

£m

£m

Preliminary Design and Planning

1.713

0.304

0.441

0.006

 

0.015

2.480

Detailed Design

-

0.155

1.075

0.420

 

0.146

1.793

Legal Fees

-

0.000

0.029

0.066

 

0.030

0.124

Land Acquisition and Compensation costs

-

-

0.021

0.123

 

0.064

0.207

Enabling works

-

-

-

0.018

 

0.172

0.189

Spend Total

1.713

0.459

1.566

0.632

 

0.427

4.798

 

ESCC has received £4.543m of LUF funding to date, as well as £0.271m Capacity and Capability funding. This would almost certainly need to be paid back if the Government do not agree to a change in project scope. Of this £3.085m has been spent so far on the project. The NPIF funding would not need to be paid back.